Power Group is vastly experienced in R & M of both thermal and hydel power plants. We are registered with Power Finance Corporation for R&M of both thermal and hydel power plants.
RANGE OF SERVICES
- RLA & LE Study and Report preparation
- R&M/RM&U Study and Report preparation
- Tender Document/ RFQ and RFP document for LROT
- Bid Evaluation
- Contract Document
- Drawing Approval
- Designers Supervision
- Inspection & Expediting
- Assistance during commissioning
EQUIPMENT AND SYSTEMS COVERED
- Boiler pressure part and auxiliaries
- Turbine, generator and auxiliaries
Balance of Plant equipment / system:
- Cooling water system, raw water system, water treatment plant, fire fighting system and DM water plant.
- Coal handling system and fuel handling system
- Ash handling system
- Air conditioning and ventilation system.
- Handling and hoisting facilities.
- Power plant electrics, control and instrumentation.
- Hydel Power Plant
Main Generating Equipment:
- Turbine, Generator, Governing System, Excitation System and Power House Auxiliaries.
Transformers and Electrical System:
- Power transformers, Auxiliary transformers, busduct, AC System, DC System, Switchyard equipment, cables, illumination system
Hydro-mechanical equipment:
- Gates, hoists, trash rack
METHODOLOGY FOR RLA &LE STUDY
- Review /Study of Design basics, Erection, first commissioning and O & M record/reports
- Hot and cold walk-down survey of the plant
- Interaction with O & M staff
- Non-destructive tests (Mechanical tests and Electrical tests on critical components, Dynamic behavior tests)
- Destructive test of Boiler pressure parts
- Evaluation and analysis of test results
- Preparation of R & M proposal
- Cost benefit analysis
MAJOR COMPLETED PROJECTS
- BOILER, TURBINE AND GENERATOR :
- 1 X 100 MW unit of Obra TPS for UPRVUNL
- 2 X 120 MW Amarkantak TPS of MPEB for Ansaldo
- 2 X 120 MW boilers of Korba East TPS of MPEB for BHEL
- 2 X 67.5 MW Boilers of BALCO CPP of NTPC
- 1 X 50 MW unit of Harduaganj TPS for UPRVUNL
- BOP AND ELECTRICS :
- 2 X 120 MW Korba (East) TPS of CSEB
- 3 X 120 MW for DVC, Chandrapura
- 2 X 120 MW Ukai TPS of GEB
- 2 X 120 MW TPS of Gandhinagar TPS, GEB
- HYDEL
- 1x40 MW Unit of Panchet HPS of DVC
- RLA study of 3x9 MW Jaldhaka Hydel Project of WBSEB.
- RLA Studies Of Pathri (3x6.8 MW) & Khatima (3x13.8 MW) Power House for UJVNL
- RLA study of four power houses in Tamil Nadu (4X35MW, 2X35 MW, 1X40MW, 1X25MW)
RLA study of 2X24 MW Hirakud Power House, Burla of OHPC |